Euraqua

Client: Euraqua (UK) Lmited

Duration: 38 weeks

Construction of steel frame B2/B8 building, including external works, and fit out.
Following demolition of an existing warehouse, the construction of a new portal
framed industrial building comprising of 800m2 warehouse and 320m2 office
space across two storeys to accommodate a relocated production/storage facility
was built.


The building was clad in Kingspan composite roof and wall panels with Kawneer
windows to the office.


Externals included concrete apron to the yard, block paved parking, security
fencing/gates and car charging facilities. A watching brief during excavations was maintained for contamination hot spots, arising from the previous usage of the site.